How do I prevent customers from working ahead?

  • 14 March 2024
  • 1 reply
  • 45 views

Userlevel 7
Badge

I have a customer that has been completing tasks where dependencies haven’t been met. (Waiting on internal things before they should be able to work on their tasks).

How do I enforce a strict rule to prevent them from working on things that aren’t ready?

icon

Best answer by emaynez 14 March 2024, 20:55

View original

1 reply

Userlevel 7
Badge

Try using Hard Dependencies!

That should prevent customers from working future tasks with incomplete dependencies.

You can enable this on your templates for in-flight projects and on the template level.

Edit Templates in an in-flight project and toggle “Hard Dependencies” on!


 

Edit Template on the Template Level (Toggle Hard Dependencies “on”)

 